How to Write an RFI That Gets Answered Fast
Write clear RFIs that don't keep bouncing back for more information
A good RFI gets answered in a few days. A bad one goes back and forth for weeks. The difference comes down to being clear, being specific, and giving the person answering everything they need upfront. Once you have a system for writing them, pair it with solid RFI tracking practices to keep everything moving. Here's how to write RFIs that actually get resolved quickly.
According to Navigant Construction Forum research, the average RFI costs $1,080 in labor to process (creation, routing, review, response, distribution). On a typical commercial project, RFIs average 10-15 days to resolve, but poorly written RFIs take 2-3x longer. FMI data shows that 30-40% of RFIs require at least one follow-up question before they can be answered—these "ping-pong" RFIs are the largest source of schedule delays.
Step 1: Make Sure You Actually Need an RFI
Before you start writing, double-check that the answer isn't already somewhere in the documents. Many unnecessary RFIs come from not fully reading the specifications:
Step 2: Write a Subject Line That Actually Says Something
The subject should tell someone exactly what the RFI is about at a glance:
• "Door question"
• "Need clarification"
• "Drawing conflict"
• "Door 104A: Hardware conflicts with schedule"
• "Level 2 corridor: Duct elevation vs beam"
• "Spec 09 29 00: Missing paint color for Rm 201"
Step 3: Explain the Problem Clearly
In your first paragraph, spell out exactly what the issue is:
Location: Grid lines, floor level, room number
Element: What specific thing is in question
Issue: What's missing, conflicting, or unclear
Impact: Why it matters and what work is affected
Step 4: Give Exact Document References
Make it easy for the person answering to find what you're talking about:
Step 5: Ask a Question That Can Actually Be Answered
End with a clear, direct question:
• "Please advise."
• "What should we do?"
• "Please clarify."
• "Should the door be 3'-0" or 2'-8"?"
• "Please confirm the correct elevation."
• "Which specification section governs?"
Step 6: Propose Solutions When You Can
Offering options speeds up the response:
"We see two options:"
A) Install 3'-0" door per schedule, adjust wall framing
B) Install 2'-8" door per plan, revise schedule
"Please confirm which approach to take, or let us know if there's another option."
Step 7: Attach Pictures and Markups
Visual attachments make your RFI much easier to understand and answer. Use PDF markup tools to highlight the exact issue:
Step 8: Explain Why It's Urgent
Help them prioritize by being clear about timing:
Frequently Asked Questions
Most construction contracts specify 7-14 days for RFI responses. AIA A201 suggests "reasonable promptness" which courts have interpreted as 7-10 business days for standard questions. Critical path items may warrant expedited response requests. Track your RFI aging—responses consistently exceeding 14 days indicate a process problem.
An RFI (Request for Information) asks for clarification or additional information about the contract documents. A submittal provides documentation (shop drawings, product data, samples) for approval before fabrication or installation. RFIs ask questions; submittals provide answers. Mixing them up delays both processes.
RFIs should clarify existing scope, not change it. If an RFI response directs work that's outside the original contract scope, it may constitute a constructive change entitling the contractor to additional compensation. Best practice: if the response materially changes scope, document it and submit a change order request referencing the RFI.
Related Resources
Better Yet, Prevent the RFI in the First Place
The best RFI is one you never have to write. Articulate's AI catches drawing conflicts and missing information during preconstruction, before they turn into field RFIs.
Catch Issues Before They Become RFIsSources & References
- • Navigant Construction Forum: The Impact of RFIs on Construction Costs and Schedule (2018)
- • FMI Corporation: Construction Industry Productivity Study (2023)
- • AIA Document A201-2017: General Conditions, Article 3.2 (Information and Services)
- • ConsensusDocs 200: Standard Agreement and General Conditions
- • AGC: RFI Best Practices for Commercial Construction