Reference Guide

Construction Change Order Guide

Understanding change orders, their types, documentation requirements, and how to manage them effectively

What is a Change Order?

A change order is a written agreement to modify the original construction contract. It adjusts the scope, cost, and/or schedule of the project. Change orders are legally binding amendments that must be agreed upon by both the owner and contractor. Many change orders originate from RFIs that uncover conflicts in the contract documents.

A Change Order Typically Includes:
  • • Description of the changed work
  • • Reason for the change
  • • Cost impact (increase or decrease)
  • • Schedule impact (days added or removed)
  • • Signatures from authorized parties

Types of Change Documents

RFIRequest for Information

A question about the contract documents. Does not change the contract, but the answer may lead to a change.

CCDConstruction Change Directive

Owner-directed change when price/time agreement hasn't been reached. Work proceeds while negotiation continues.

PCOPotential Change Order

Contractor-initiated notice of a potential change. Documents the issue and estimated impact before formal pricing.

COChange Order

The formal, signed amendment to the contract. Includes agreed-upon cost, schedule, and scope changes.

ASIArchitect's Supplemental Instruction

Minor clarification or change that doesn't affect cost or schedule. If cost/time is impacted, becomes a change order.

Common Causes of Change Orders

Owner-Caused
  • • Scope additions or deletions
  • • Material upgrades
  • • Schedule acceleration
  • • User requirement changes
Design-Caused
  • • Drawing errors or omissions
  • • Coordination conflicts
  • • Code compliance issues
  • • Specification conflicts
Field-Caused
  • • Unforeseen conditions
  • • Existing conditions differ
  • • Utility conflicts
  • • Soil/groundwater issues
External-Caused
  • • Code changes during construction
  • • Permit requirements
  • • Material unavailability
  • • Labor disputes

The Change Order Process

1
Identify the Change

Document what changed, why, and who requested it. Reference RFIs, ASIs, or field conditions.

2
Quantify the Impact

Prepare detailed cost breakdown and schedule analysis. Include labor, materials, equipment, overhead, and profit.

3
Submit Pricing

Formal proposal with backup documentation. Include quotes, labor rates, and productivity assumptions.

4
Negotiate

Review and negotiate terms. Owner may request additional backup or value engineering.

5
Execute

Sign change order and incorporate into project budget and schedule. Update contract sum.

6
Track

Monitor change order work separately. Document actual costs vs. estimated for future reference.

Change Order Pricing Methods

MethodDescriptionBest For
Lump SumFixed price for defined scopeClear, well-defined changes
Unit PriceRate × quantityRepetitive work, unknown quantities
Time & MaterialsActual costs + markupEmergency work, unknown scope
Not-to-ExceedT&M with capUncertain scope with budget limit

Reducing Change Orders

The best change order is the one you prevent. A thorough constructability review during preconstruction is the most effective way to reduce change orders:

  • Thorough preconstruction review — Catch coordination issues before construction starts
  • Clear specifications — Reduce ambiguity that leads to disputes
  • Owner decision deadlines — Prevent late changes that cost more
  • Regular coordination meetings — Catch conflicts early
  • Accurate existing condition surveys — Know what you're working with

Related Resources

Prevent Design-Caused Change Orders

Most change orders stem from coordination conflicts and errors in drawings. Articulate's AI catches these issues during preconstruction—when fixing them costs dollars, not thousands.

Start Catching Issues Early